External terrace refurbishment
- Artek were responsible for reconfiguration of existing trellis concealment to house high voltage electrical feed for new substation.
- Artek manufactured and installed bespoke fabricated steel gallow supports.
- Artek were responsible for complete surface refurbishment of exiting stone work / features.
- Artek refurbished ALL external timber terrace furniture .
- Artek replaced Piccadilly elevation of decorative trellis with full colour match redecoration.
- Artek supplied and fitted new antique mirrors into stone recessed panels.
- Artek provided full logistical support via ROYAL PARKS management for goods in and out for the duration of the works.
Refurbishment of back of house staff ladies changing rooms.
- Artek managed full strip out and refit of staff changing rooms as per client led design.
- Full surface refurbishment.
- Full electrical rewire with new lighting accommodation.
- Installation of comprehensive fixtures and fitting applicable to the daily operations of such a facility.
- Comprehensive test and commission of all systems.
Walk in chiller enabling
- Artek were required to strip out an existing space to allow for incoming chiller install by SPECIALIST REFRIGERATION SUPPLIER.
- Artek were responsible for full demolition, reconfiguration and decommission of all services as per architects plans.
- Artek handed over ‘working envelope’ space to allow chiller install.
Miscellaneous
- Office conversion to second floor comprising new meeting and conference rooms with additional w/c and staff relaxation rooms. Full project / procurement management over a 6 week programme delivery.
- Main kitchen – ceiling replacement, lighting upgrade & chefs office reconfiguration, full project management within extremely restricted out of hours working window.
- Full test and commission upon project completion.
- Casino & Club – bespoke joinery install comprising new reception desks & concierge station. Complete design ,manufacture and install of bespoke furniture to clients exacting specifications.
- Basement – waterproof tanking application to storage vaults. Full project management comprising Vault preparation, specialist membrane and tanking install, test and commission of completed project.
- Casino & Club – Security / staff signing in office refurbishment. Full project management from decommission and strip out to fit out. M&E, HVAC, Joinery & viewing station. Work station configuration and ALL security requirements.